Manchester
March 2012 ... THE QUESTIONS ASKED OF THE LOCAL AUTHORITY
informationcompliance@manchester.gov.uk
1. Has your Local Authority agreed an indicative budget for LHW for the period April 2013 - March 2015?
2. If an indicative budget has been agreed for LHW for the period April 2013 – March 2015, what sum has been agreed?
3. What arrangements have been agreed by your Local Authority for supporting your local LINk during transition to LHW for the period April 2012 – March 2013?
4. What arrangements has your Local Authority put in place to include the local LINk in the pilot Health and Wellbeing Board for the Authority’s area?
5. How many meetings have taken place with the public in your Authority’s area to consult them on the development of LHW?
Note: ‘Arrangements’ mean a provision or plan made in preparation for an undertaking
informationcompliance@manchester.gov.uk
1. Has your Local Authority agreed an indicative budget for LHW for the period April 2013 - March 2015?
2. If an indicative budget has been agreed for LHW for the period April 2013 – March 2015, what sum has been agreed?
3. What arrangements have been agreed by your Local Authority for supporting your local LINk during transition to LHW for the period April 2012 – March 2013?
4. What arrangements has your Local Authority put in place to include the local LINk in the pilot Health and Wellbeing Board for the Authority’s area?
5. How many meetings have taken place with the public in your Authority’s area to consult them on the development of LHW?
Note: ‘Arrangements’ mean a provision or plan made in preparation for an undertaking
LOCAL AUTHORITY CONTRIBUTION ...
1. An indicative budget has not yet been agreed.
2. No response
3. We have continued to support the local LINk during the transition period. The Strategic Director has met with the LINk.
4. None.
5. We are meeting in April 2012 to consult on the development of LHW and will be carrying out further consultations with the public.
2. No response
3. We have continued to support the local LINk during the transition period. The Strategic Director has met with the LINk.
4. None.
5. We are meeting in April 2012 to consult on the development of LHW and will be carrying out further consultations with the public.
UPDATE FROM:
THE HEALTHWATCH IMPLEMENTATION PROGRAMME TEAM October 2012
To read the full report (67 pages), click here ... |
Add to the contribution/s
To add to - or to update/comment on a contribution - submit your entry to Malcolm Alexander, Chair, NALM
__________________________________________________________________________________
Please state clearly:
1. The name of your Local Authority, LINk or Host
2. Your name
3. Your position within the Local Authority, LINk or Host
4. Your email address
5. Your telephone number
To add to - or to update/comment on a contribution - submit your entry to Malcolm Alexander, Chair, NALM
__________________________________________________________________________________
Please state clearly:
1. The name of your Local Authority, LINk or Host
2. Your name
3. Your position within the Local Authority, LINk or Host
4. Your email address
5. Your telephone number